Question 5) Certified Associate in Project Management

Posted on
Like what you see? Share it.Share on Google+Share on LinkedInShare on FacebookShare on RedditTweet about this on TwitterEmail this to someone

Objective: Project Closing
SubObjective: Close Project

Single Answer Multiple Choice

Which of the following is NOT an input of the Close Project process?

A. contract documentation
B. project management plan
C. formal acceptance of the final product, service, or result
D. organizational process assets

Answer:
C. formal acceptance of the final product, service, or result

Tutorial:
The formal acceptance of the final product, service, or result is not an input of the Close Project process. Formal acceptance is an output of the Close Project process.

The inputs of the Close Project process are the project management plan, contract documentation, enterprise environmental factors, organizational process assets, work performance information, and deliverables.

Reference:
A Guide to the Project Management Body of Knowledge – PMBOK Guide 3rd Edition – Project Integration Management – 4.7 Close Project

These questions are derived from the Self Test Software Practice Test for PMI exam #CAPM3ED – Certified Associate in Project Management, Third Edition

Like what you see? Share it.Share on Google+Share on LinkedInShare on FacebookShare on RedditTweet about this on TwitterEmail this to someone
cmadmin

ABOUT THE AUTHOR

Posted in Archive|

Comment: