Project Planning
These questions are derived from the Self Test Software Practice Test for the Project Management Institute exam #PMP3ED – Project Management Professional Third Edition
Objective : Project Planning
SubObjective : Schedule Development
Single Answer, Multiple Choice
One of your project’s tasks has an Early Start of week 9, an Early Finish of week 15, a Late Start of week 12, and a Late Finish of week 18. What is the task’s float?
- 3
- 6
- 9
- 12
Answer:
A. 3
Tutorial:
The task’s float is 3. Float, or slack is defined as the amount of time that a particular task can slip before the critical path is affected. Basically, this is how long a task can be delayed without affecting the overall finish date of the project. You can calculate the slack for an activity using LS – ES or LF – EF. In this scenario, the task has a Late Start of week 12 and an Early Start of week 9. You can use the formula LS – ES, which yields float for the task of 12 – 9, or 3. Using the formula LF – EF yields an identical result.
All of the other options are incorrect because they do not reflect the correct float calculation.
Reference:
1. A Guide to the Project Management Body of Knowledge – PMBOK Guide 3rd Edition – Project Time Management – 6.5.2 Schedule Development: Tools and Techniques